Until we start updating the HOT NEWS page with information on
our move to Trosper Park, you will be able to find the latest news about
the move here. Please let us know if you have any questions contact the
webmaster.
Timeline
Initial Parks & Rec. meeting, June 24, 2006
Oklahoma City Parks & Recreation Commission vote to lease the former
Trosper BMX land, August 16, 2006.
Track Rules and Regs written, September 6, 2006
Track Rules and Regs submitted for approval, September 8, 2006
Lease 'draft' includes Rules & Regs, September 18, 2006
Lease 'draft' returned to Parks & Rec., December 21, 2006
Revised lease submitted to Parks & Rec., January 12, 2007
Parks & Rec. requests insurance certificate, January 19, 2007
Insurance certificate submitted for approval, April 17, 2007
Insurance certificate revised for approval, June 6, 2007
Insurance certificate revised for approval, June 24, 2007
Oklahoma City Council vote to accept Trosper Lease, July 17, 2007
Received actual lease paperwork, July 25, 2007
Notice of vacate date for South Western location, September 6, 2007
Oklahoma City Riverfront Redevelopment Authority vote to terminate
South Western lease, September 25, 2007
Date of preliminary Trosper Park Use Map, November 20, 2007
Order placed for sign at Trosper Park, November 27, 2007
Date of ODOT preliminary filing, December 5, 2007
Date of 1st work at Trosper Park December 8, 2007
Date of this page was first posted, December 10, 2007
Date of Preliminary Building design start, December 11, 2007
Date of ODOT filing, December 14, 2007
Official vacate date, December 15, 2007
Turn over keys to ODOT, December 18, 2007
OGE notified to remove service, December 19, 2007
Date of 1st WORK DAY, December 29, 2007
Date of 2nd WORK DAY, December 30, 2007
Date of 3rd WORK DAY, January 7, 2008
Date of 4th WORK DAY, January 13, 2008
ODOT relocation received, January 14, 2008
Initial park plan submitted, January 15, 2008
ODOT moving received, January 17, 2008
ATT change order to cut phone service at old track, January 17, 2008
OG&E recalled on 'old' service cut off, January 18, 2008
Business cards on order, January 18, 2008
Initial park plan approved, January 22, 2008
Date of 1st Trosper pictures posted to web site, January 27, 2008
Initial Plan posted to web site, January 27, 2008
Track location final staking, January 27, 2008
SJOC 1st contact, January 29, 2008
SJOC 2nd contact - Steve Vaughan, February 6, 2008
Business cards received, February 7, 2008
SJOC call back, February 8, 2008
SJOC 1st meeting, February 14, 2008
Major drainage survey, February 17, 2008
Clean up of west side of property begun, February 17, 2008
Request for metal building price (Clark), February 18, 2008
Order placed for equipment, March 4, 2008
Trailer ready for pick-up, March 8, 2008
Prep begins on tow vehicle, March 11, 2008
Metal building price quote, March 17, 2008
Tow vehicle repair completed, March 20, 2008
Trailer and BOBCAT purchased, March 23, 2008
Trailer rehab begins, March 31, 2008
Met neighbor (Murray Allison), April 3, 2008
Trailer rehab complete, April 4, 2008
Mowing and clearing brush, April 5, 2008
WORK DAY, April 6, 2008 1PM
1st donated dirt used for fill and some mowing, April 6, 2008
Trailer rehab really complete, April 7, 2008
1st Contact OKC Streets on drainage (Moulder) April 11, 2008
Contact Oklahoma ONECALL (underground location service) April 11, 2008
WORK DAY, April 12, 2008
Water meter located, April 14, 2008
Marked culvert and ditch locations, April 15, 2008
WORK DAY, April 19, 2008 1PM
First work in clearing track pad, April 19, 2008
WORK DAY, April 20, 2008 1PM
First work on south landscaping, April 20, 2008
Contact Streets about culverts, April 21, 2008
Water meter dig, April 21-22, 2008
Meeting with Streets Dept. about culverts, April 23, 2008
Front of property filled and leveled, April 26, 2008
Front work area partially raked, April 27, 2008
WORK DAY, May 1, 2008 (Cancelled due to weather)
WORK DAY, May 2, 2008 (Cancelled due to wet conditions)
WORK DAY, May 3, 2008
WORK DAY, May 4, 2008
Plumbing contractor contacted, May 6, 2008
City Streets drainage reply, May 7, 2008
Excavating contractor contacted, May 7, 2008
Excavating contractor on site meeting, May 9, 2008
Storm water permit paperwork picked up, May 12, 2008
OGE contact, May 12, 2008
OGE 1st on-site meeting, May 13, 2008
OGE on-site service assessment, May 14, 2008
Pick up of Dixon mower, May 15, 2008
1st use of Dixon mower, May 16, 2008
SWPPP work begins, May 19, 2008
Existing Topo map generated, May 19-21, 2008
Revised Topo map started May 22, 2008
Plumber out to look at sight, May 30, 2008
WORK DAY, June 7, 2008
WORK DAY, June 8, 2008
Dixon serviced-new belts and blades sharpened, June 9, 2008
Clean up and mowing, June 9, 2008
Meeting with City Parks Dept., June 11, 2008
SWPPP filed and permit issued, June 11, 2008
Plumbing quotes received, June 11, 2008
WORK DAY, June 14, 2008
OG&E wants to meet again, June 17, 2008
Post hole for temp electric pole dug, June 17, 2008
Excavator wants to meet again, June 18, 2008
Dumpster delivered, June 18, 2008
Heavy duty trailer purchased for Bobcat, June 19, 2008
WORK DAY, June 22, 2008
WORK DAY, June 23, 2008
Excavator meeting, June 24, 2008
DEQ contact, June 25, 2008
WORK DAY, June 28, 2008
WORK DAY, June 29, 2008
Dixon repair parts ordered, July 03, 2008
WORK DAY, July 05, 2008
WORK DAY, July 06, 2008
More work on electric service, July 07, 2008
Weed clearing, July 08, 2008
Left messages at DEQ about permit, July 17, 2008
Contact DEQ about permit, July 18, 2008
Repair to Dixon blade shaft, July 19, 2008
Repair Dixon deck, July 20, 2008
WORK DAY, July 20, 2008
WORK DAY, July 21, 2008
WORK DAY, July 26, 2008
WORK DAY, July 27, 2008
Contact DEQ about permit, August 1, 2008
WORK DAY, August 02, 2008
WORK DAY, August 03, 2008
Dumpster removed, August 05, 2008
Heavy duty trailer for Bobcat stolen, August 7, 2008
Contact DEQ about permit, August 8, 2008
Left messages at DEQ about permit, August 8, 2008
WORK DAY, August 09, 2008
WORK DAY, August 10, 2008
OERB contact, contractor name and number received, August 11, 2008
Excavator to start work in about 10 days, August 13, 2008
OG&E contacted about work, August 15, 2008
OERB contractor contacted (left message), August 15, 2008
SJOC contacted about marking pipelines, August 15, 2008
WORK DAY, August 16, 2008
WORK DAY, August 17, 2008
OERB contractor contacted, August 18, 2008
WORK DAY, August 22, 2008
WORK DAY, August 23, 2008
WORK DAY, August 24, 2008
Oklahoma Corporation Commission contacted us about well site, August 26, 2008
Oklahoma Corporation Commission site visit, August 26, 2008
WORK DAY, August 30, 2008
WORK DAY, August 31, 2008
WORK DAY, September 01, 2008
WORK DAY, September 05, 2008
WORK DAY, September 06, 2008
WORK DAY, September 07, 2008
Excavation work continued, 1st culvert installed, September 08, 2008
Excavation work continued, 2nd culvert installed, September 09, 2008
75 tons of gravel delivered to site, September 10, 2008
Official copy of DEQ permit received in mail, September 10, 2008
Potential new trailer inspected, September 11, 2008
WORK DAY, September 12, 2008 (rain out)
Work on Bobcat repairs, September 12, 2008
WORK DAY, September 13, 2008 (rain out)
Potential new trailer inspected, September 13, 2008
Bobcat repaired, September 14, 2008
WORK DAY, September 14, 2008
WORK DAY, September 19, 2008
WORK DAY, September 20, 2008
WORK DAY, September 21, 2008
Dixon mower repaired, September 27, 2008 (cancelled)
WORK DAY, September 28, 2008
OG&E contact, October 07, 2008
WORK DAY, October 11, 2008
WORK DAY, October 12, 2008
WORK DAY, October 18, 2008
WORK DAY, October 26, 2008
WORK DAY, November 1, 2008
WORK DAY, November 2, 2008
WORK DAY, November 8, 2008 (cancelled)
WORK DAY, November 9, 2008 (cancelled)
WORK DAY, November 15, 2008 (cancelled)
WORK DAY, November 16, 2008
Site work for electric service and track, November 22, 2008
WORK DAY, November 23, 2008
WORK DAY, November 29, 2008 (cancelled to attend 2008 Grand National)
WORK DAY, November 30, 2008 (cancelled to attend 2008 Grand National)
Demolishion of OLD Sooner Pearl complete, December 1, 2008
50 tons of gravel delivered to site, December 2, 2008
Heavy equipment rented, December 4, 2008
Dirt purchased (5000 yards), December 4, 2008
WORK DAY, December 6, 2008
WORK DAY, December 7, 2008
Electric easement cleared, December 7, 2008
DIRT DAY, December 11, 2008
OG&E easement inspection, December 11, 2008
DIRT DAY, December 12, 2008
CLEANING DAY, December 13, 2008
CLEANING DAY, December 14, 2008
DIRT DAY, December 19, 2008
1/2 DIRT DAY, December 20, 2008
Jump building starts, December 28, 2008
DIRT DAY, December 29, 2008
DIRT DAY, December 30, 2008
1/2 Dirt on site, December 30, 2008
DIRT DAY, December 31, 2008
WORK DAY, January 1, 2009
DIRT DAY, January 2, 2009
FINAL DIRT DAY, January 3, 2009
WORK DAY, January 4, 2009
OG&E work survey, January 5, 2009
© 2001-2008 Red Oak Resources, All Rights Reserved.
Last updated Tuesday January 06,2009 12:10 AM
Build date Monday December 10,2007 01:21 AM
Trademarks and registered trademarks are property of their registered owners.