Timeline
Initial Parks & Rec. meeting, June 24, 2006
Oklahoma City Parks & Recreation Commission vote to lease the former
Trosper BMX land, August 16, 2006.
Track Rules and Regs written, September 6, 2006
Track Rules and Regs submitted for approval, September 8, 2006
Lease 'draft' includes Rules & Regs, September 18, 2006
Lease 'draft' returned to Parks & Rec., December 21, 2006
Revised lease submitted to Parks & Rec., January 12, 2007
Parks & Rec. requests insurance certificate, January 19, 2007
Insurance certificate submitted for approval, April 17, 2007
Insurance certificate revised for approval, June 6, 2007
Insurance certificate revised for approval, June 24, 2007
Oklahoma City Council vote to accept Trosper Lease, July 17, 2007
Received actual lease paperwork, July 25, 2007
Notice of vacate date for South Western location, September 6, 2007
Oklahoma City Riverfront Redevelopment Authority vote to terminate
South Western lease, September 25, 2007
Date of preliminary Trosper Park Use Map, November 20, 2007
Order placed for sign at Trosper Park, November 27, 2007
Date of ODOT preliminary filing, December 5, 2007
Date of 1st work at Trosper Park December 8, 2007
Date of this page was first posted, December 10, 2007
Date of Preliminary Building design start, December 11, 2007
Date of ODOT filing, December 14, 2007
Official vacate date, December 15, 2007
Turn over keys to ODOT, December 18, 2007
OGE notified to remove service, December 19, 2007
Date of 1st WORK DAY, December 29, 2007
Date of 2nd WORK DAY, December 30, 2007
Date of 3rd WORK DAY, January 7, 2008
Date of 4th WORK DAY, January 13, 2008
ODOT relocation received, January 14, 2008
Initial park plan submitted, January 15, 2008
ODOT moving received, January 17, 2008
ATT change order to cut phone service at old track, January 17, 2008
OG&E recalled on 'old' service cut off, January 18, 2008
Business cards on order, January 18, 2008
Initial park plan approved, January 22, 2008
Date of 1st Trosper pictures posted to web site, January 27, 2008
Initial Plan posted to web site, January 27, 2008
Track location final staking, January 27, 2008
SJOC 1st contact, January 29, 2008
SJOC 2nd contact - Steve Vaughan, February 6, 2008
Business cards received, February 7, 2008
SJOC call back, February 8, 2008
SJOC 1st meeting, February 14, 2008
Major drainage survey, February 17, 2008
Clean up of west side of property begun, February 17, 2008
Request for metal building price (Clark), February 18, 2008
Order placed for equipment, March 4, 2008
Trailer ready for pick-up, March 8, 2008
Prep begins on tow vehicle, March 11, 2008
Metal building price quote, March 17, 2008
Tow vehicle repair completed, March 20, 2008
Trailer and BOBCAT purchased, March 23, 2008
Trailer rehab begins, March 31, 2008
Met neighbor (Murray Allison), April 3, 2008
Trailer rehab complete, April 4, 2008
Mowing and clearing brush, April 5, 2008
WORK DAY, April 6, 2008 1PM
1st donated dirt used for fill and some mowing, April 6, 2008
Trailer rehab really complete, April 7, 2008
1st Contact OKC Streets on drainage (Moulder) April 11, 2008
Contact Oklahoma ONECALL (underground location service) April 11, 2008
WORK DAY, April 12, 2008
Water meter located, April 14, 2008
Marked culvert and ditch locations, April 15, 2008
WORK DAY, April 19, 2008 1PM
First work in clearing track pad, April 19, 2008
WORK DAY, April 20, 2008 1PM
First work on south landscaping, April 20, 2008
Contact Streets about culverts, April 21, 2008
Water meter dig, April 21-22, 2008
Meeting with Streets Dept. about culverts, April 23, 2008
Front of property filled and leveled, April 26, 2008
Front work area partially raked, April 27, 2008
WORK DAY, May 1, 2008 (Cancelled due to weather)
WORK DAY, May 2, 2008 (Cancelled due to wet conditions)
WORK DAY, May 3, 2008
WORK DAY, May 4, 2008
Plumbing contractor contacted, May 6, 2008
City Streets drainage reply, May 7, 2008
Excavating contractor contacted, May 7, 2008
Excavating contractor on site meeting, May 9, 2008
Storm water permit paperwork picked up, May 12, 2008
OGE contact, May 12, 2008
OGE 1st on-site meeting, May 13, 2008
OGE on-site service assessment, May 14, 2008
Pick up of Dixon mower, May 15, 2008
1st use of Dixon mower, May 16, 2008
SWPPP work begins, May 19, 2008
Existing Topo map generated, May 19-21, 2008
Revised Topo map started May 22, 2008
Plumber out to look at sight, May 30, 2008
WORK DAY, June 7, 2008
WORK DAY, June 8, 2008
Dixon serviced-new belts and blades sharpened, June 9, 2008
Clean up and mowing, June 9, 2008
Meeting with City Parks Dept., June 11, 2008
SWPPP filed and permit issued, June 11, 2008
Plumbing quotes received, June 11, 2008
WORK DAY, June 14, 2008
OG&E wants to meet again, June 17, 2008
Post hole for temp electric pole dug, June 17, 2008
Excavator wants to meet again, June 18, 2008
Dumpster delivered, June 18, 2008
Heavy duty trailer purchased for Bobcat, June 19, 2008
WORK DAY, June 22, 2008
WORK DAY, June 23, 2008
Excavator meeting, June 24, 2008
Excavating quotes received, June 24, 2008
DEQ contact, June 25, 2008
WORK DAY, June 28, 2008
WORK DAY, June 29, 2008
Dixon repair parts ordered, July 03, 2008
WORK DAY, July 05, 2008
WORK DAY, July 06, 2008
More work on electric service, July 07, 2008
Weed clearing, July 08, 2008
Left messages at DEQ about permit, July 17, 2008
Contact DEQ about permit, July 18, 2008
Repair to Dixon blade shaft, July 19, 2008
Repair Dixon deck, July 20, 2008
WORK DAY, July 20, 2008
WORK DAY, July 21, 2008
WORK DAY, July 26, 2008
WORK DAY, July 27, 2008
Contact DEQ about permit, August 1, 2008
WORK DAY, August 02, 2008
WORK DAY, August 03, 2008
Gate chain and locks removed by Parks, August 4, 2008
Dumpster removed, August 05, 2008
Cleared post hole for electric pole, August 5, 2008
Heavy duty trailer for Bobcat stolen, August 7, 2008
Contact DEQ about permit, August 8, 2008
Left messages at DEQ about permit, August 8, 2008
WORK DAY, August 09, 2008
WORK DAY, August 10, 2008
OERB contact, contractor name and number received, August 11, 2008
Notified by DEQ permit authorized, August 12, 2008
Received DEQ permit via email, August 13, 2008
Notified excavator of DEQ permit authorization, August 13, 2008
Excavator to start work in about 10 days, August 13, 2008
OG&E contacted about work, August 15, 2008
OERB contractor contacted (left message), August 15, 2008
SJOC contacted about marking pipelines, August 15, 2008
WORK DAY, August 16, 2008
WORK DAY, August 17, 2008
OERB contractor contacted, August 18, 2008
WORK DAY, August 22, 2008
WORK DAY, August 23, 2008
WORK DAY, August 24, 2008
Plumber asked to install waterline, August 26, 2008
Oklahoma Corporation Commission contacted us about well site, August 26, 2008
Oklahoma Corporation Commission site visit, August 26, 2008
SJOC marked pipelines, August 28, 2008
WORK DAY, August 30, 2008
WORK DAY, August 31, 2008
WORK DAY, September 01, 2008
Ditch marking complete, September 02, 2008
Excavation work delayed due to rain, September 03, 2008
Excavation work started, September 05, 2008
Bobcat work, work was started on 1st straight drainage. September 05, 2008
More Bobcat work around pad, added dirt to pad. September 06, 2008
WORK DAY, September 07, 2008
Excavation work continued, 1st culvert installed, September 08, 2008
Excavation work continued, 2nd culvert installed, September 09, 2008
75 tons of gravel delivered to site, September 10, 2008
Official copy of DEQ permit received in mail, September 10, 2008
Potential new trailer inspected, September 11, 2008
WORK DAY, September 12, 2008 (rain out)
Work on Bobcat repairs, September 12, 2008
WORK DAY, September 13, 2008 (rain out)
Potential new trailer inspected, September 13, 2008
Bobcat repaired, September 14, 2008
WORK DAY, September 14, 2008
Water line ditched and laid, September 18, 2008
WORK DAY, September 19, 2008
WORK DAY, September 20, 2008
WORK DAY, September 21, 2008
Dixon mower repaired, September 27, 2008 (cancelled)
Started work on track drainage, September 28, 2008
OG&E contact, October 07, 2008
OG&E start work with City for new powerlines, October 10, 2008
Raked ditch at sign location, October 11, 2008
Worked on ditches,worked to leveled staging area, October 12, 2008
WORK DAY, October 18, 2008
Worked to leveled staging area, October 18, 2008
Worked on sign area and front ditch, October 18, 2008
WORK DAY, October 26, 2008
Worked on clearing brush, October 26, 2008
More contact with OERB about well site clean-up, October 30, 2008
WORK DAY, November 1, 2008
WORK DAY, November 2, 2008
Old pipeline discovered, November 2, 2008
WORK DAY, November 8, 2008 (cancelled)
WORK DAY, November 9, 2008 (cancelled)
Meeting on site OG&E about new electric service, November 13, 2008
WORK DAY, November 15, 2008 (cancelled)
WORK DAY, November 16, 2008
Site work for electric service and track, November 22, 2008
WORK DAY, November 23, 2008
WORK DAY, November 29, 2008 (cancelled to attend 2008 Grand National)
WORK DAY, November 30, 2008 (cancelled to attend 2008 Grand National)
Demolishion of OLD Sooner Pearl complete, December 1, 2008
50 tons of gravel delivered to site, December 2, 2008
Heavy equipment rented (Pioneer), December 4, 2008
Dirt purchased (5000 yards), December 4, 2008
WORK DAY, December 6, 2008
First berm started, December 6, 2008
WORK DAY, December 7, 2008
Electric easement cleared, December 7, 2008
DIRT DAY, December 11, 2008
5000 yards of dirt - 1st delivery, December 11, 2008
OG&E easement inspection, December 11, 2008
DIRT DAY, December 12, 2008
CLEANING DAY, December 13, 2008
CLEANING DAY, December 14, 2008
DIRT DAY, December 19, 2008
1/2 DIRT DAY, December 20, 2008
Jump building starts, December 28, 2008
DIRT DAY, December 29, 2008
DIRT DAY, December 30, 2008
1/2 Dirt on site, December 30, 2008
DIRT DAY, December 31, 2008
WORK DAY, January 1, 2009
DIRT DAY, January 2, 2009
FINAL DIRT DAY, January 3, 2009
WORK DAY, January 4, 2009
OG&E work survey, January 5, 2009
WORK EVENING, January 5, 2009
WORK EVENING, January 6, 2009
WORK EVENING, January 7, 2009
WORK EVENING, January 9, 2009
WORK DAY, January 10, 2009
WORK DAY, January 11, 2009
Contact ABA about track build, January 11, 2009
WORK EVENING, January 12, 2009
OG&E starts on site work, January 12, 2009
OERB says work to start in about 45 days, January 12, 2009
WORK DAY (dozer work), January 13, 2009
WORK DAY (dozer work), January 14, 2009
OERB final inspection before job bidding, January 14, 2009
WORK DAY (dozer work), January 15, 2009
Small loader picked up (Pioneer), January 15,2009
WORK DAY (dozer work), January 16, 2009
WORK DAY (dozer work), January 17, 2009
WORK DAY (dozer work), January 18, 2009
ABA thinks Billy Allen can build track, January 18, 2009
WORK DAY (dozer work), January 19, 2009
WORK DAY (dozer work), January 20, 2009
ABA commits Billy Allen to build track, January 20, 2009
WORK DAY (dozer work), January 21, 2009
Rented 3.5 yard loader, January 21, 2009
OERB job bidding, January 21, 2009
WORK DAY (dozer work), January 22, 2009
3.5 yard loader delivered, January 22, 2009
Billy Allen starts track build (1/2 day), January 22, 2009
Track cleared, January 22, 2009
Dirt added to starting hill, January 22, 2009
Pad work, January 22, 2009
WORK DAY (dozer work), January 23, 2009
Billy Allen track build (full day), January 23, 2009
Pad work and 1st turn, January 23, 2009
WORK DAY (dozer work), January 24, 2009
Billy Allen track build (full day), January 24, 2009
1st straight jumps and 2nd turn, January 24, 2009
3.5 yard loader BROKE, January 24, 2009
WORK DAY (dozer work), January 25, 2009
North ditch, January 25, 2009
WORK DAY (dozer work), January 26, 2009
North ditch, January 26, 2009
WORK DAY (dozer work), January 28, 2009
North ditch, January 28, 2009
3.5 yard loader picked up (Hertz), January 28, 2009
WORK DAY (dozer work), January 29, 2009
North ditch roughin complete, January 29, 2009
Dozer picked up (Pioneer), January 29, 2009
Dirt payment completed, February 5, 2009
4 wheeler returns, February 12, 2009
WORK EVENING Raised area on nouth side, February 18, 2009
WORK EVENING February 19, 2009
Billy Allen is back, February 19, 2009
Mud hole is draining, February 19, 2009
WORK DAY (track build), February 20, 2009
3.5 yard loader delivered, February 20, 2009
Drained mud hole in 1st turn, February 20, 2009
WORK DAY (track build), February 21, 2009
Billy Allen continues track build (full day), February 21, 2009
3rd turn and pad built, February 21, 2009
Last straight jumps built, February 21, 2009
WORK DAY (track build), February 22, 2009
WORK EVENING Raised area on south side, February 25, 2009
WORK EVENING Raised area on south side, February 26, 2009
rhythm section built, February 22, 2009
2nd straight started, February 22, 2009
PRO set started, February 22, 2009
Last straight gets some packing, February 22, 2009
WORK DAY (track build), February 23, 2009
2nd straight finished, February 23, 2009
PRO set finished, February 23, 2009
Dirt added to starting hill, February 23, 2009
Billy Allen finishes track build (full day), February 23, 2009
WORK EVENING Raised area on south side, February 25, 2009
WORK EVENING Raised area on south side, February 26, 2009
WORK DAY, March 1, 2009
WORK EVENING (drainage), March 2, 2009
Called to have Loader picked up, March 2, 2009
Loader picked up, March 5, 2009
WORK EVENING (drainage), March 6, 2009
WORK DAY, March 7, 2009
Work on north side ditch, March 7, 2009
WORK DAY, March 8, 2009
Worked on supply pile and drainage on east side of track, March 8, 2009
Purchased power rake #1, March 8, 2009
Received quote on storage building, March 9, 2009
Storage building ordered, March 10, 2009
Received power rake #1, March 13, 2009
WORK DAY, March 14, 2009
Purchased power rake #2, March 16, 2009
Drainage pipe material request for quote, March 17, 2009
Received power rake #2, March 18, 2009
Storage building ready for pickup, March 19, 2009
Storage building sheet goods picked up, March 20, 2009
Wellsite cleanup begins, March 20, 2009
Measured for gate forms and steel, March 22, 2009
WORK DAY, March 22, 2009
Measured for gate forms and steel, March 22, 2009
Wellsite cleanup work, March 23, 2009
Storage building sheet goods stored, March 23, 2009
Drainage pipe bid request, March 26, 2009
Drainage pipe bid received, March 27, 2009
WORK DAY, March 29, 2009
Track surface work, March 29, 2009
Drainage pipe ordered, March 30, 2009
Drainage pipe delivered, April 3, 2009
WORK DAY, April 4, 2009
Track drainage work, April 4, 2009
WORK DAY, April 5, 2009
Track drainage work, April 5, 2009
Project 'Plot plan' printed, April 8, 2009
Building permit applied for, April 9, 2009
WORK DAY, April 11, 2009
Track drainage work, April 11, 2009
Project 'Plans' work, April 12, 2009
Project 'Plans' work, April 15, 2009
Storage building framing goods picked up, April 17, 2009
Some building framing goods unloaded, April 17, 2009
WORK DAY, April 18, 2009
Track drainage work (1st turn), April 18, 2009
Added dirt to small south platform, April 18, 2009
WORK DAY, April 19, 2009
Track drainage work (3rd turn), April 19, 2009
Last building framing goods unloaded, April 19, 2009
Loaded excess drainage pipe, fittings today. , April 23, 2009
Completion old well site clean up, April 24, 2009
Returned unused drainage pipe, April 24, 2009
Well site clean up equipment removed, April 28, 2009
Track drainage pipe paid, May 1, 2009
Mowing equipment maintenance, May 9, 2009
1st mowing of 2009, May 10, 2009
Mowing and weedeating, May 24, 2009
Trash dumped at track, June 9, 2009
Mowing, June 20, 2009
Meeting with City officials, June 24, 2009
Bobcat work on ditches and landscaping, June 28, 2009
Work day, July 5, 2009
Work day, July 12, 2009
Contact Attorney Dennis Box (voice mail), August 21, 2009
Attorney Dennis Box meeting, September 1, 2009
Dennis Box (refused to help, letter), October 1, 2009
© 2001-2010 Red Oak Resources, All Rights Reserved.
Last updated Thursday January 28,2010 11:58 PM
Build date Monday December 10,2007 01:21 AM
Trademarks and registered trademarks are property of their registered owners.