Sooner Pearl BMX Raceway at Trosper Park
Information about our move to Trosper Park
Until we start updating the HOT NEWS page with information on our move to Trosper Park, you will be able to find the latest news about the move here. Please let us know if you have any questions contact the webmaster.
Timeline
Initial Parks & Rec. meeting, June 24, 2006
Oklahoma City Parks & Recreation Commission vote to lease the former Trosper BMX land, August 16, 2006.
Track Rules and Regs written, September 6, 2006
Track Rules and Regs submitted for approval, September 8, 2006
Lease 'draft' includes Rules & Regs, September 18, 2006
Lease 'draft' returned to Parks & Rec., December 21, 2006
Revised lease submitted to Parks & Rec., January 12, 2007
Parks & Rec. requests insurance certificate, January 19, 2007
Insurance certificate submitted for approval, April 17, 2007
Insurance certificate revised for approval, June 6, 2007
Insurance certificate revised for approval, June 24, 2007
Oklahoma City Council vote to accept Trosper Lease, July 17, 2007
Received actual lease paperwork, July 25, 2007
Notice of vacate date for South Western location, September 6, 2007
Oklahoma City Riverfront Redevelopment Authority vote to terminate South Western lease, September 25, 2007
Date of preliminary Trosper Park Use Map, November 20, 2007
Order placed for sign at Trosper Park, November 27, 2007
Date of ODOT preliminary filing, December 5, 2007
Date of 1st work at Trosper Park December 8, 2007
Date this page was first posted, December 10, 2007
Date of Preliminary Building design start, December 11, 2007
Date of ODOT filing, December 14, 2007
Official vacate date, December 15, 2007
Turn over keys to ODOT, December 18, 2007
OGE notified to remove service, December 19, 2007
Date of 1st WORK DAY, December 29, 2007
Date of 2nd WORK DAY, December 30, 2007
Date of 3rd WORK DAY, January 7, 2008
Date of 4th WORK DAY, January 13, 2008
ODOT relocation received, January 14, 2008
Initial park plan submitted, January 15, 2008
ODOT moving received, January 17, 2008
ATT change order to cut phone service at old track, January 17, 2008
OG&E recalled on 'old' service cut off, January 18, 2008
Business cards on order, January 18, 2008
Initial park plan approved, January 22, 2008
Date of 1st Trosper pictures posted to web site, January 27, 2008
Initial Plan posted to web site, January 27, 2008
Track location final staking, January 27, 2008
SJOC 1st contact, January 29, 2008
SJOC 2nd contact - Steve Vaughan, February 6, 2008
Business cards received, February 7, 2008
SJOC call back, February 8, 2008
SJOC 1st meeting, February 14, 2008
Major drainage survey, February 17, 2008
Clean up of west side of property begun, February 17, 2008
Request for metal building price (Clark), February 18, 2008
Order placed for equipment, March 4, 2008
Trailer ready for pick-up, March 8, 2008
Prep begins on tow vehicle, March 11, 2008
Metal building price quote, March 17, 2008
Tow vehicle repair completed, March 20, 2008
Official WORK BEGINNING DATE, March 22, 2008
Trailer and BOBCAT purchased, March 23, 2008
Trailer rehab begins, March 31, 2008
Met neighbor (Murray Allison), April 3, 2008
Trailer rehab complete, April 4, 2008
Mowing and clearing brush, April 5, 2008
WORK DAY, April 6, 2008 1PM
1st donated dirt used for fill and some mowing, April 6, 2008
Trailer rehab really complete, April 7, 2008
1st Contact OKC Streets on drainage (Moulder) April 11, 2008
Contact Oklahoma ONECALL (underground location service) April 11, 2008
WORK DAY, April 12, 2008
Water meter located, April 14, 2008
Marked culvert and ditch locations, April 15, 2008
WORK DAY, April 19, 2008 1PM
First work in clearing track pad, April 19, 2008
WORK DAY, April 20, 2008 1PM
First work on south landscaping, April 20, 2008
Contact Streets about culverts, April 21, 2008
Water meter dig, April 21-22, 2008
Meeting with Streets Dept. about culverts, April 23, 2008
Front of property filled and leveled, April 26, 2008
Front work area partially raked, April 27, 2008
WORK DAY, May 1, 2008 (Cancelled due to weather)
WORK DAY, May 2, 2008 (Cancelled due to wet conditions)
WORK DAY, May 3, 2008
WORK DAY, May 4, 2008
Plumbing contractor contacted, May 6, 2008
City Streets drainage reply, May 7, 2008
Excavating contractor contacted, May 7, 2008
Excavating contractor on site meeting, May 9, 2008
Storm water permit paperwork picked up, May 12, 2008
OGE contact, May 12, 2008
OGE 1st on-site meeting, May 13, 2008
OGE on-site service assessment, May 14, 2008
Pick up of Dixon mower, May 15, 2008
1st use of Dixon mower, May 16, 2008
SWPPP work begins, May 19, 2008
Existing Topo map generated, May 19-21, 2008
Revised Topo map started May 22, 2008
Plumber out to look at sight, May 30, 2008
WORK DAY, June 7, 2008
WORK DAY, June 8, 2008
Dixon serviced-new belts and blades sharpened, June 9, 2008
Clean up and mowing, June 9, 2008
Meeting with City Parks Dept., June 11, 2008
SWPPP filed and permit issued, June 11, 2008
Plumbing quotes received, June 11, 2008
WORK DAY, June 14, 2008
OG&E wants to meet again, June 17, 2008
Post hole for temp electric pole dug, June 17, 2008
Excavator wants to meet again, June 18, 2008
Dumpster delivered, June 18, 2008
Heavy duty trailer purchased for Bobcat, June 19, 2008
WORK DAY, June 22, 2008
WORK DAY, June 23, 2008
Excavator meeting, June 24, 2008
Excavating quotes received, June 24, 2008
DEQ contact, June 25, 2008
WORK DAY, June 28, 2008
WORK DAY, June 29, 2008
Dixon repair parts ordered, July 03, 2008
WORK DAY, July 05, 2008
WORK DAY, July 06, 2008
More work on electric service, July 07, 2008
Weed clearing, July 08, 2008
Left messages at DEQ about permit, July 17, 2008
Contact DEQ about permit, July 18, 2008
Repair to Dixon blade shaft, July 19, 2008
Repair Dixon deck, July 20, 2008
WORK DAY, July 20, 2008
WORK DAY, July 21, 2008
WORK DAY, July 26, 2008
WORK DAY, July 27, 2008
Contact DEQ about permit, August 1, 2008
WORK DAY, August 02, 2008
WORK DAY, August 03, 2008
Old Sooner Pearl buildings vandalized (open), August 2 or 3, 2008
Gate chain and locks removed by Parks, August 4, 2008
Dumpster removed, August 05, 2008
Gate chain and locks still gone, August 5, 2008
Cleared post hole for electric pole, August 5, 2008
Heavy duty trailer for Bobcat stolen, August 7, 2008
Contact DEQ about permit, August 8, 2008
Left messages at DEQ about permit, August 8, 2008
WORK DAY, August 09, 2008
WORK DAY, August 10, 2008
OERB contact, contractor name and number received, August 11, 2008
Notified by DEQ permit authorized, August 12, 2008
Received DEQ permit via email, August 13, 2008
Notified excavator of DEQ permit authorization, August 13, 2008
Excavator to start work in about 10 days, August 13, 2008
OG&E contacted about work, August 15, 2008
OERB contractor contacted (left message), August 15, 2008
SJOC contacted about marking pipelines, August 15, 2008
WORK DAY, August 16, 2008
WORK DAY, August 17, 2008
OERB contractor contacted, August 18, 2008
WORK DAY, August 22, 2008
WORK DAY, August 23, 2008
WORK DAY, August 24, 2008
Path for our waterline cleared, August 24, 2008
Plumber asked to install waterline, August 26, 2008
Oklahoma Corporation Commission contacted us about well site, August 26, 2008
Oklahoma Corporation Commission site visit, August 26, 2008
SJOC marked pipelines, August 28, 2008
WORK DAY, August 30, 2008
WORK DAY, August 31, 2008
WORK DAY, September 01, 2008
Ditch marking complete, September 02, 2008
Excavation work delayed due to rain, September 03, 2008
Excavation work started, September 05, 2008
Bobcat work, work was started on 1st straight drainage. September 05, 2008
More Bobcat work around pad, added dirt to pad. September 06, 2008
WORK DAY, September 07, 2008
Excavation work continued, 1st culvert installed, September 08, 2008
Excavation work continued, 2nd culvert installed, September 09, 2008
75 tons of gravel delivered to site, September 10, 2008
Official copy of DEQ permit received in mail, September 10, 2008
Potential new trailer inspected, September 11, 2008
WORK DAY, September 12, 2008 (rain out)
Work on Bobcat repairs, September 12, 2008
WORK DAY, September 13, 2008 (rain out)
Potential new trailer inspected, September 13, 2008
Bobcat repaired, September 14, 2008
WORK DAY, September 14, 2008
Water line ditched and laid, September 18, 2008
WORK DAY, September 19, 2008
WORK DAY, September 20, 2008
WORK DAY, September 21, 2008
Temp electric pole installed, September 21, 2008
Dixon mower repaired, September 27, 2008 (cancelled)
Started work on track drainage, September 28, 2008
OG&E contact, October 07, 2008
1st contact at old track with contractor, October 09, 2008
OG&E start work with City for new powerlines, October 10, 2008
Raked ditch at sign location, October 11, 2008
Worked on ditches,worked to leveled staging area, October 12, 2008
WORK DAY, October 18, 2008 Worked to leveled staging area, October 18, 2008
Worked on sign area and front ditch, October 18, 2008
WORK DAY, October 26, 2008
Worked on clearing brush, October 26, 2008
More contact with OERB about well site clean-up, October 30, 2008
WORK DAY, November 1, 2008
WORK DAY, November 2, 2008
Old pipeline discovered, November 2, 2008
WORK DAY, November 8, 2008 (cancelled)
WORK DAY, November 9, 2008 (cancelled)
Meeting on site OG&E about new electric service, November 13, 2008
WORK DAY, November 15, 2008 (cancelled)
WORK DAY, November 16, 2008
Site work for electric service and track, November 22, 2008
WORK DAY, November 23, 2008
WORK DAY, November 29, 2008 (cancelled to attend 2008 Grand National)
WORK DAY, November 30, 2008 (cancelled to attend 2008 Grand National)
Demolishion of OLD Sooner Pearl complete, December 1, 2008
50 tons of gravel delivered to site, December 2, 2008
Heavy equipment rented (Pioneer), December 4, 2008
Dirt purchased (5000 yards), December 4, 2008
WORK DAY, December 6, 2008
First berm started, December 6, 2008
WORK DAY, December 7, 2008
Electric easement cleared, December 7, 2008
DIRT DAY, December 11, 2008
5000 yards of dirt - 1st delivery, December 11, 2008
OG&E easement inspection, December 11, 2008 DIRT DAY, December 12, 2008
CLEANING DAY, December 13, 2008
CLEANING DAY, December 14, 2008
DIRT DAY, December 19, 2008
1/2 DIRT DAY, December 20, 2008
Jump building starts, December 28, 2008
DIRT DAY, December 29, 2008
DIRT DAY, December 30, 2008
1/2 Dirt on site, December 30, 2008
DIRT DAY, December 31, 2008
WORK DAY, January 1, 2009
DIRT DAY, January 2, 2009
FINAL DIRT DAY, January 3, 2009
WORK DAY, January 4, 2009
OG&E work survey, January 5, 2009
WORK EVENING, January 5, 2009
WORK EVENING, January 6, 2009
WORK EVENING, January 7, 2009
WORK EVENING, January 9, 2009
WORK DAY, January 10, 2009
WORK DAY, January 11, 2009
 Contact ABA about track build, January 11, 2009
WORK EVENING, January 12, 2009
 OG&E starts on site work, January 12, 2009
OERB says work to start in about 45 days, January 12, 2009
WORK DAY (dozer work), January 13, 2009
WORK DAY (dozer work), January 14, 2009
 OERB final inspection before job bidding, January 14, 2009
WORK DAY (dozer work), January 15, 2009
 Small loader picked up (Pioneer), January 15,2009
WORK DAY (dozer work), January 16, 2009
WORK DAY (dozer work), January 17, 2009
WORK DAY (dozer work), January 18, 2009
 ABA thinks Billy Allen can build track, January 18, 2009
WORK DAY (dozer work), January 19, 2009
WORK DAY (dozer work), January 20, 2009
 ABA commits Billy Allen to build track, January 20, 2009
WORK DAY (dozer work), January 21, 2009
 Rented 3.5 yard loader, January 21, 2009
Contacted Architect, January 21, 2009
 OERB job bidding, January 21, 2009
WORK DAY (dozer work), January 22, 2009
 3.5 yard loader delivered, January 22, 2009
 Billy Allen starts track build (1/2 day), January 22, 2009
 Track cleared, January 22, 2009
 Dirt added to starting hill, January 22, 2009
 Pad work, January 22, 2009
WORK DAY (dozer work), January 23, 2009
 Billy Allen track build (full day), January 23, 2009
 Pad work and 1st turn, January 23, 2009
WORK DAY (dozer work), January 24, 2009
 Billy Allen track build (full day), January 24, 2009
 1st straight jumps and 2nd turn, January 24, 2009
 3.5 yard loader BROKE, January 24, 2009
WORK DAY (dozer work), January 25, 2009
 North ditch, January 25, 2009
WORK DAY (dozer work), January 26, 2009
 North ditch, January 26, 2009
WORK DAY (dozer work), January 28, 2009
 North ditch, January 28, 2009
 3.5 yard loader picked up (Hertz), January 28, 2009
WORK DAY (dozer work), January 29, 2009
 North ditch roughin complete, January 29, 2009
 Dozer picked up (Pioneer), January 29, 2009
Dirt payment completed, February 5, 2009
4 wheeler returns, February 12, 2009
WORK EVENING Raised area on nouth side, February 18, 2009
WORK EVENING February 19, 2009
 Billy Allen is back, February 19, 2009
 Mud hole is draining, February 19, 2009
WORK DAY (track build), February 20, 2009
 3.5 yard loader delivered, February 20, 2009
 Drained mud hole in 1st turn, February 20, 2009
WORK DAY (track build), February 21, 2009
 Billy Allen continues track build (full day), February 21, 2009
 3rd turn and pad built, February 21, 2009
 Last straight jumps built, February 21, 2009
WORK DAY (track build), February 22, 2009
WORK EVENING Raised area on south side, February 25, 2009
WORK EVENING Raised area on south side, February 26, 2009
 rhythm section built, February 22, 2009
 2nd straight started, February 22, 2009
 PRO set started, February 22, 2009
 Last straight gets some packing, February 22, 2009
WORK DAY (track build), February 23, 2009
 2nd straight finished, February 23, 2009
 PRO set finished, February 23, 2009
 Dirt added to starting hill, February 23, 2009
 Billy Allen finishes track build (full day), February 23, 2009
WORK EVENING Raised area on south side, February 25, 2009
WORK EVENING Raised area on south side, February 26, 2009
WORK DAY, March 1, 2009
WORK EVENING (drainage), March 2, 2009
 Called to have Loader picked up, March 2, 2009
Loader picked up, March 5, 2009
WORK EVENING (drainage), March 6, 2009
WORK DAY, March 7, 2009
 Work on north side ditch, March 7, 2009
WORK DAY, March 8, 2009
 Worked on supply pile and drainage on east side of track, March 8, 2009
 Purchased power rake #1, March 8, 2009
Received quote on storage building, March 9, 2009
Hinges for new gate bought, March 9, 2009
Storage building ordered, March 10, 2009
Received power rake #1, March 13, 2009
WORK DAY, March 14, 2009
Purchased power rake #2, March 16, 2009
Material for new gate purchased (cyl mount), March 16, 2009
Drainage pipe material request for quote, March 17, 2009
Big loader rental paid, March 17, 2009
Received power rake #2, March 18, 2009
Gate cylinder mounts fabricated (eye brackets), March 18, 2009
Storage building ready for pickup, March 19, 2009
Gate material ordered, March 20, 2009
Storage building sheet goods picked up, March 20, 2009
Wellsite cleanup begins, March 20, 2009
 Measured for gate forms and steel, March 22, 2009
WORK DAY, March 22, 2009
 Measured for gate forms and steel, March 22, 2009
Wellsite cleanup work, March 23, 2009
Storage building sheet goods stored, March 23, 2009
Gate material received, March 25, 2009
Drainage pipe bid request, March 26, 2009
Drainage pipe bid received, March 27, 2009
WORK DAY, March 29, 2009
 Track surface work, March 29, 2009
Drainage pipe ordered, March 30, 2009
Drainage pipe delivered, April 3, 2009
WORK DAY, April 4, 2009
 Track drainage work, April 4, 2009
WORK DAY, April 5, 2009
 Track drainage work, April 5, 2009
Gate material prep started, April 7, 2009
Project 'Plot plan' printed, April 8, 2009
Building permit applied for, April 9, 2009
WORK DAY, April 11, 2009
 Track drainage work, April 11, 2009
Project 'Plans' work, April 12, 2009
Gate build started, April 13, 2009
Project 'Plans' work, April 15, 2009
Storage building framing goods picked up, April 17, 2009
Some building framing goods unloaded, April 17, 2009
WORK DAY, April 18, 2009
 Track drainage work (1st turn), April 18, 2009
 Added dirt to small south platform, April 18, 2009
WORK DAY, April 19, 2009
 Track drainage work (3rd turn), April 19, 2009
Last building framing goods unloaded, April 19, 2009
Gate work (fabrication), April 21, 2009
Loaded excess drainage pipe, fittings today. , April 23, 2009
Completion old well site clean up, April 24, 2009
Returned unused drainage pipe, April 24, 2009
Well site clean up equipment removed, April 28, 2009
Gate work (welding), May 1, 2009
Track drainage pipe paid, May 1, 2009
Gate work (welding), May 3, 2009
Gate work (drawings), May 4, 2009
Gate work (cylinder 'eye brackets' welded), May 9, 2009
Mowing equipment maintenance, May 9, 2009
1st mowing of 2009, May 10, 2009
Gate work (upper cylinder mount welded), May 11, 2009
Gate work (lower cylinder mount welded), May 13, 2009
Gate work (expanded metal welding completed), May 13, 2009
Mowing and weedeating, May 24, 2009
Gate work (welding completed), May 30, 2009
Gate work (delivered to track), June 1, 2009
Trash dumped at track, June 9, 2009
Water hole work, June 11, 2009
Gate painted black, June 14, 2009
Mowing, June 20, 2009
Meeting with City officials, June 24, 2009
Bobcat work on ditches and landscaping, June 28, 2009
Work day, July 5, 2009
Work day, July 12, 2009
Contact Attorney Dennis Box (voice mail), August 21, 2009
Attorney Dennis Box (meeting scheduled), August 28, 2009
Attorney Dennis Box meeting, September 1, 2009
Dennis Box (refused to help, letter), October 1, 2009
Contact Attorney, October 27, 2009
Attorney meeting scheduled, October 29, 2009
Attorney meeting, November 3, 2009
Attorney calls back with news, November 9, 2009
Bought copies of official Corp. documents from State, November 13, 2009
Updated official Corp. documents with State, November 13, 2009
Received 'filed' copy of updated Corp. docs, November 18, 2009
Copy of corp. docs to Donald Nevard, November 20, 2009
Copy of OKC Trosper Park deed docs to Donald Nevard, November 27, 2009
Copy of 2002 Trosper lease docs to Donald Nevard, December 3, 2009
Draft of Trosper lease PUD from Donald Nevard, December 8, 2009
Returned draft of Trosper PUD to Donald Nevard, December 15, 2009
Revised Trosper PUD from Donald Nevard, December 16, 2009
Check for Trosper lease PUD to OKC via Donald Nevard 2350, December 17, 2009
Questions from OKC on new track, December 30, 2009
Insurance docs on special forms, January 7, 2010
Signed paperwork and paid fee to renew Trosper lease, January 7, 2010
Bobcat in for repair, January 15, 2010
PUD revised, January 26, 2010
PUD plans revised, January 26, 2010
Bobcat out from repair, February 5, 2010
Renewal of Trosper lease till 2014, February 7, 2010
PUD vote by OKC Planning Commission (passed), February 11, 2010
WORK DAY, February 13, 2010
City Council preliminary PUD vote, March 9, 2010
WORK DAY, March 6, 2010
WORK DAY, March 13, 2010
WORK DAY, March 20, 2010
City Council final PUD vote and passage, March 30, 2010
WORK DAY, surveying of start hill, April 4, 2010
Official copy of PUD 1410 in mail, April 6, 2010
WORK DAY, April 11, 2010
WORK DAY, April 11, 2010
Contacted Bobby at SE Maint. shop, April 14, 2010
 Talked about grass clean-up, he OK'd Round-up use.
Contacted Donnie at SE Mower shop, April 14, 2010
 Talked post and cable barrier and equipment.
 Talked about post and cable barrier and purchasing posts.
Bought FM tuner for PA system, April 17, 2010
Bought AMP and speakers for PA system, April 18, 2010
Located posts for post and cable barrier, April 19, 2010
First attempt on water permit, April 21, 2010
Purchased posts for post and cable barrier, April 23, 2010
FM tuner for PA system arrives, April 23, 2010
AMP and speakers for PA system arrives, April 24, 2010
Unloaded posts for post and cable barrier, April 25, 2010
CD player donated for PA system (Figard), April 27, 2010
Started to kill grass on track, April 27, 2010
More killing grass on track, April 29, 2010
Building permit application, April 30, 2010
Talked to Brad about insurance papers, April 30, 2010
New insurance papers, May 3, 2010
Work on building permit, May 7, 2010
Starting hill work, May 8, 2010
Work on building permit, May 14, 2010
Kill grass, May 20, 2010
Equipment work, May 22, 2010
Begins mowing season, May 23, 2010
Storm water call for meeting, May 27, 2010
Storm water meeting, May 28, 2010
More track clearing work, May 30, 2010
Kill grass, May 30, 2010
Building permit work, June 4, 2010
More track clearing work, June 6, 2010
Kill grass, June 6, 2010
Kill grass, June 7, 2010
Building permit meeting, June 11, 2010
Clear track and weedeat, June 12, 2010
Building permit purchased (BLDC-2010-02120), June 18, 2010
PA rack work, June 20, 2010
Water service work, July 27, 2010
Water service work, June 29, 2010
Water service work, July 02, 2010
PA rack work, July 03, 2010
Gate form work, July 05, 2010
Water service permits bought (PLMC-2010-00696), July 06, 2010
Mowing, July 14, 2010
Mower work, July 17, 2010
Work day, July 18, 2010
Mowing and dirt work, July 18, 2010
Work day, July 24, 2010
Mowing and ditch work, July 24, 2010
Mower work, July 24, 2010
Work day, July 25, 2010
Ditch work, July 25, 2010
Bobcat maintenance, July 25, 2010
PA work, July 29, 2010
Work day, August 1, 2010
Work day, August 3, 2010
Work day, August 4, 2010
Work day, August 5, 2010
OG&E account set up, August 5, 2010
Work day, August 7, 2010
Remove water line and redig ditch, August 7, 2010
Work day, August 8, 2010
Remove water line and redig ditch, August 8, 2010
Work day, August 11, 2010
Remove water line and redig ditch, August 11, 2010
Work day, August 14, 2010
Remove water line and redig ditch, August 14, 2010
Ordered Cartessa 'TARA' box, August 19, 2010
Work day, August 22, 2010
Work on starting hill, August 22, 2010
New TARA controller arrives, August 25, 2010
Water line inspection , August 27, 2010
Work evening, August 29, 2010
Starting hill work, August 29, 2010
Work evening, August 30, 2010
Starting hill work, August 30, 2010
Gate cylinder repairs start, August 30, 2010
Work evening, August 31, 2010
Starting hill work, August 31, 2010
Gate cylinder repairs, August 31, 2010
Work evening, September 1, 2010
Water line work, September 1, 2010
Work evening, September 2, 2010
Water line work, September 2, 2010
Work evening, September 3, 2010
Water line work, September 3, 2010
Water service date (no service), September 7, 2010
Mower repairs, September 12, 2010
Mower repairs, September 16, 2010
Water service (new pipe?), September 16, 2010
Water box hole, September 22, 2010
Water box hole, September 23, 2010
Electric service work start, September 23, 2010
Work day, September 26, 2010
Work day, September 27, 2010
Work day, October 3, 2010
Work day, October 4, 2010
Work day, October 5, 2010
Work day, October 6, 2010
Water service completed today (FINAL PLMC-2010-00696), October 6, 2010
Work day, October 7, 2010
Work day, October 8, 2010
Work day, October 9, 2010
Work day, October 10, 2010
Repaired chemical sprayer, October 17, 2010
Repaired trailer lights, October 17, 2010
Bill from Parks for lease, October 20, 2010
Final payment for water line, October 21, 2010
Work day, October 24, 2010
--> New elctrician contacted, October 25, 2010
Work day, October 27, 2010
Work day, October 28, 2010
Off track work day, November 2, 2010
Work day, November 3, 2010
Work day, November 4, 2010
Temp electric pole rebuilt (2nd time), November 4, 2010
Inspection day, no, November 5, 2010
Work day, November 7, 2010
Work day, November 8, 2010
Electric permit fee paid to contractor, November 10, 2010
Work day, November 14, 2010
Work day, November 16, 2010
Electric permit (ELEC-2010-06921) , November 17, 2010
Work day, November 22, 2010
Work day, November 23, 2010
Work day, December 30, 2010
Work day, December 31, 2010
Work day, January 1, 2011
Electric service, January 3, 2011
Electric service, January 5, 2011
Work day, January 8, 2011
Work day, January 14, 2011
Work day, January 15, 2011
Work day, January 17, 2011
Electric service work, January 18, 2011
3/4 ton truck purchased, January 18, 2011
Work day, January 19, 2011
Work day, January 22, 2011
Work day, January 24, 2011
Work day, January 25, 2011
Work day, January 26, 2011
Work day, January 27, 2011
Work day, January 28, 2011
Work day, January 29, 2011
Electric service stand plans, February 3, 2011
Electric service stand metal purchased, February 11, 2011
Work day, February 12, 2011
Work day, February 13, 2011
Electric service stand fabricated, February 15, 2011
Electric service stand cleaned and painted, February 16, 2011
Electric service stand packaged and delivered, February 17, 2011
Work day, February 18, 2011
Work day, February 19, 2011
Work day, February 20, 2011
Work day, February 21, 2011
Work day, February 22, 2011
Work day, February 23, 2011
Bobcat work day
Work day, February 26, 2011
Work day, February 27, 2011
Work day, February 28, 2011
Work day, March 1, 2011
Work day, March 2, 2011
Updated electricial contractor on record with city
Work day, March 4, 2011
Installed stand/boxes for electricial service
Work day, March 5, 2011
Work day, March 6, 2011
Work day, March 7, 2011
Electricial FINAL inspection
OG&E account call for service (no)
Work day, March 8, 2011
Work day, March 9, 2011
Work day, March 10, 2011
Work day, March 11, 2011
Work day, March 12, 2011
Work day, March 13, 2011
Work day, March 14, 2011
OG&E was notified today on electric service
Work day, March 15, 2011
Work day, March 16, 2011
Work day, March 17, 2011
Met OG&E was notified on dirt work
Completed dirt work
Work day, March 18, 2011
Met OG&E, marked trench location
Work day, March 19, 2011
Work day, March 20, 2011
Work day, March 21, 2011
Work day, March 22, 2011
Work day, March 23, 2011
Work day, March 24, 2011
Electric service completed.
Work day, March 25, 2011
Fence permit purchased.
Work day, March 26, 2011
Work day, April 1, 2011
Work day, April 2, 2011
Work day, April 3, 2011
Work day, April 5, 2011
Work day, April 6, 2011
Work day, April 7, 2011
Work day, April 8, 2011
Work day, April 9, 2011
Work day, April 13, 2011
Work day, April 14, 2011
Work day, April 16, 2011
Work day, April 17, 2011
Work day, April 19, 2011
Work day, April 20, 2011
Work day, April 21, 2011
Work day, April 22, 2011
Work day, April 23, 2011
Work day, April 25, 2011
Work day, April 26, 2011
Work day, April 27, 2011
Work day, April 28, 2011
Work day, April 30, 2011
Work day, May 2, 2011
Work day, May 3, 2011
Work day, May 4, 2011
Work day, May 5, 2011
Work day, May 6, 2011
Work day, May 7, 2011
Work day, May 8, 2011
Work day, May 10, 2011
Work day, May 12, 2011
Work day, May 13, 2011
Work day, May 14, 2011
Work day, May 15, 2011
Work day, May 16, 2011
Work day, May 17, 2011
Work day, May 18, 2011
Work day, May 19, 2011
Work day, May 21, 2011
Work day, May 22, 2011
Work day, May 24, 2011
Work day, May 25, 2011
Work day, May 26, 2011
Work day, May 28, 2011
Work day, May 29, 2011
Work day, May 31, 2011
Work day, June 1, 2011
Work day, June 2, 2011
Work day, June 5, 2011
Prefab work on gate forms begin
Work day, June 7, 2011
Work day, June 8, 2011
Work day, June 9, 2011
Install work on gate forms begin
Work day, June 10, 2011
N-O-T stormwater (city) filed today.
Work day, June 11, 2011
Bobcat work
Work day, June 12, 2011
Gate slab rough dirt work complete.
Work day, June 13, 2011
Work day, June 14, 2011
Work day, June 15, 2011
Work day, June 16, 2011
Work day, June 17, 2011
Work day, June 18, 2011
Work day, June 20, 2011
Work day, June 21, 2011
Work day, June 22, 2011
Work day, June 23, 2011
Work day, June 24, 2011
Work day, June 25, 2011
Work day, June 26, 2011
Work day, June 27, 2011
N-O-T stormwater (city) filed today.
Work day, June 28, 2011
Work day, June 29, 2011
Work day, June 30, 2011
Work day, July 1, 2011
Work day, July 2, 2011
Drop gate forms begin off track.
Gate area compacted for 2nd time.
Work day, July 4, 2011
Drop gate located on start hill.
Work day, July 5, 2011
Work day, July 6, 2011
Work day, July 7, 2011
Work day, July 8, 2011
Work day, July 9, 2011
Work day, July 11, 2011
Work day, July 13, 2011
Gate slab rebar work begins.
Work day, July 14, 2011
Form work complete.
Drains for drop gate installed.
Gravel under slab loaded and roughed in.
Stormwater deq final inspection.
Work day, July 15, 2011
Work day, July 16, 2011
Gravel leveled.
Rebar tying begins.
Work day, July 17, 2011
All prep for concrete completed on starting hill.
Bobcat debris removal.
Concrete contractor site inspection.
Work day, July 18, 2011
Contractor hired for gate concrete pore
Final track debris removal started.
Work day, July 19, 2011
Starting hill work area cleaned of debris.
Work day, July 20, 2011
Started work on the Porta-Potty enclosure slab forms.
Contractor orders concrete for gate pore on Friday 8am
Work day, July 21, 2011
Finished the Porta-Potty enclosure slab forms.
Finished all work for the Porta-Potty enclosure slab, ready for concrete.
Work day, July 22, 2011
Worked on a new shaded area east of staging.
Moved dirt to the starting hill for fill and leveling.
Watered the top of the starting hill.
Contractor pores concrete for the gate at 7:30am.
Contractor pores concrete for the Porta-Potty enclosure slab.
Work day, July 23, 2011
Started work on starting hill to fill and level.
Watered the top of the starting hill.
Starting hill work area cleaned of debris.
Removed outer concrete forms for the gate.
Removed most of the inner 'cut-out' concrete forms for the gate.
Work day, July 25, 2011
Track grass and weed clearing, 1st straight.
Work day, July 26, 2011
Started rework of wiring for air cylinder.
Work day, July 27, 2011
Moved more dirt to starting hill to fill and level.
Watered the top of the starting hill.
Work day, July 28, 2011
Finished removal of the inner 'cut-out' concrete forms for the gate.
Watered the top of the starting hill.
Finished drains for the 'cut-out' in the gate.
Work day, July 29, 2011
Added more dirt and shaped the back of the starting.
Watered the top of the starting hill.
Cleared brush on north side of track.
Work day, July 30, 2011
Shaped and packed dirt on the back side (staging) of the starting hill.
Work day, July 31, 2011
Watered the front of the starting hill.
Shaped and packed dirt on the front of the starting hill.
Worked on cleaning up loose material in 1st straight ahead of grooming work.
Work day, August 1, 2011
Watered the top of the starting hill.
Work day, August 2, 2011
Watered the top of the starting hill.
Work day, August 3, 2011
No work today.
Work day, August 4, 2011
Work begins on front of starting hill.
Watered the back of the starting hill.
Work day, August 5, 2011
Work on Porta-potty enclosure fence post holes begins.
Work day, August 6, 2011
Work on Porta-potty enclosure fence post holes.
Watered the back of the starting hill.
Work day, August 7, 2011
Work on Porta-potty enclosure fence post holes.
Watered the back of the starting hill.
Work day, August 8, 2011
No work today.
Work day, August 9, 2011
Work on Porta-potty enclosure fence post holes.
Watered the back of the starting hill.
Work day, August 10, 2011
Work on Porta-potty enclosure fence post holes.
Watered the back of the starting hill.
Work day, August 11, 2011
Work on Porta-potty enclosure fence post holes.
Watered the back of the starting hill.
Work day, August 12, 2011
No work today.
Work day, August 13, 2011
No work today.
Work day, August 14, 2011
No work today.
Work day, August 20, 2011
Porta-potty enclosure work started.
Work day, August 21, 2011
Porta-potty enclosure work.
Work day, August 22, 2011
Porta-potty enclosure work.
Work day, August 23, 2011
No work today.
Work day, August 24, 2011
No work today.
Work day, August 25, 2011
Porta-potty enclosure work completion.
Work day, August 26, 2011
All major work on new track completed.
Time to close out all our open permits.
Work day, August 27, 2011
Track clearing work.
Work day, August 28, 2011
Work on 2nd straight.
Work day, September 2, 2011
Track clearing work.
Work day, September 3, 2011
Work on last straight.
Work day, September 4, 2011
Work on last straight.
Work day, September 5, 2011
Pack work.
Work day, September 10, 2011
Work on 2nd turn.
Work day, September 11, 2011
Work on 2nd turn.
Work day, September 13, 2011
Work on 2nd turn.
Work day, September 17, 2011
Work on 2nd turn and 3rd straight.
Work day, September 18, 2011
Work on 2nd turn and 3rd straight.
Work day, October 4, 2011
Electric permit FINAL today.
Work day, October 7, 2011
Building permit FINAL today.
All permits are closed and we have a Certificate of Occupancy.
Work day, October 15, 2011
Last turn racked.
Work day, October 16, 2011
Last turn racked and packed.
Work day, October 29, 2011
1st turn work.
Work day, October 30, 2011
1st turn work.
1st turn packed.
Work day, November 5, 2011
Starting gate slab work.
Work day, November 6, 2011
Starting gate slab work.
Final concrete poured to finish starting gate slab work.
Work day, November 12, 2011
Rework on track after rain.
Work day, November 13, 2011
Rework on track after rain.
Work day, November 19, 2011
Work on 1st straight.
Work day, November 20, 2011
Work on 1st straight.
Unofficial PRACTICE without operating gate.
Work day, December 4, 2011
Official 2012 race schedule filed.
Opening date announced, January 1, 2012
Rework on track after rain.
Work day, December 17, 2011
Track surface finish work begins.
Work day, December 18, 2011
Track surface finish work.
Work day, December 31, 2011
Track surface finish work.
1st track dragging today.
OPENING/RACE day, January 1, 2012
1ST RACE ON NEW TRACK.
PRACTICE day, January 7, 2012
1ST PRACTICE ON NEW TRACK.
RACE day, January 8, 2012
PRACTICE day, January 14, 2012
RACE day, January 15, 2012
© 2001-2012 Red Oak Resources, All Rights Reserved.
Last updated Tuesday, January 17, 2012 10:03:06 PM
Build date Monday December 10,2007 01:21 AM
Trademarks and registered trademarks are property of their registered owners.
E-mail about this site: webmaster